SAMPLE SITE NOTES (fictional) - Residential block, Sector 62, Noida - week ending 14 Nov

Mon: 4th floor slab shuttering 80% done. Steel for 4th floor slab received - 12.5 MT, checked against delivery challan. 2 carpenters absent.
Tue: Slab rebar tying started grids A-D. Plumbing sleeves for 4th floor not yet placed - plumber to come Wed.
Wed: Plumber placed sleeves grids A-C. Grids D-F pending - waiting for revised drawing P-104 rev C from consultant.
Thu: Concrete pour planned Sat cancelled - RMC plant says no supply Sat. Rescheduled to Mon 17 Nov, 7 am. Cube moulds ready (6 nos).
Fri: Brickwork 2nd floor 65% done. Safety: two workers without harness at 3rd floor edge, stopped work, toolbox talk held.
Sat: Lift shaft wall shuttering 3rd-4th floor done.
Decisions needed: (1) revised P-104 rev C for sleeves D-F by Mon; (2) client to confirm balcony railing sample (2 samples on site).