# What is a defects liability period?

Source: https://cloudbrain.in/glossary/defects-liability-period
Last updated: 2026-11-22

The defects liability period (DLP) is a period after completion, set in the construction contract, during which the contractor must correct defects that appear in the works at its own cost. Its start and end dates, and the retention held against it, need to be tracked.

## Why does defects liability period matter in a construction project audit?

Defects notified within the period are usually the contractor's responsibility, so its start and end dates, and the retention held against it, need to be tracked and a defects inspection planned before it ends.

## What is an example?

A contract sets a twelve-month defects liability period from the completion certificate, with half of the retention released at completion and the rest after defects are corrected at the end of the period.

## Where does CloudBrain come in?