What do we check on industrial projects?
- Design and structure: foundations and structure for heavy loads and long spans, roofing and cladding, and design against the codes that apply where the project is.
- Process and services interfaces: equipment foundations, openings, loads, utilities, and coordination with mechanical, electrical, fire and plumbing services.
- Fire safety and approvals: fire protection design and installation, and the factory, environmental and building approvals with their conditions.
- Quality: concrete, steel and roofing quality records, and workmanship on site.
- Billing and contracts: milestone and measurement-based billing, variations, and EPC or design-and-build payment terms.
- Schedule: fast-track programmes, long-lead items and the critical path.
| Project types | Factories, warehouses and logistics parks, plants and process buildings, cold stores |
|---|---|
| Typical focus | Structure and foundations, process and services interfaces, fire safety, approvals, fast-track billing |
| Stages | Pre-construction, construction and post-construction, one stage or all of them |
| Delivery | Document review remotely, with site inspections in India directly and elsewhere by arrangement |

What are the key risks at each stage?
| Stage | Typical risks on industrial projects |
|---|---|
| Pre-construction | Foundations and floors not designed for equipment loads; process and services interfaces unresolved; approvals missing from the programme |
| Construction | Fast-track pressure on quality records; milestone bills ahead of actual progress; late design changes for process equipment |
| Post-construction | Incomplete commissioning of fire and utility systems; as-builts that do not show process changes |
Which codes and standards do we check against?
For projects in India, we check against the codes and standards that apply, such as the National Building Code of India 2016 (including Part 4 on fire and life safety), IS 456 for concrete, IS 800 for steel, IS 875 for design loads and IS 1893 for earthquake resistance, along with local building bye-laws. Outside India, we check against the codes and standards that apply where the project is. Industrial projects also need the factory, fire and environmental approvals that apply, and we check their conditions.
What does a typical finding look like?
These are illustrative examples, not from a real project.
Floor slab designed for general storage loads; the equipment layout shows heavy racking point loads
- Evidence
- Structural design basis compared with the racking supplier's load data
- Recommendation
- Recheck the slab design for the actual point loads before construction
Pre-engineered building milestone billed as complete while roof sheeting is still in progress
- Evidence
- Milestone bill compared with site inspection and the progress report
- Recommendation
- Hold the milestone payment until completion is verified
Fire approval conditions for the storage area are not reflected in the sprinkler design
- Evidence
- Fire approval conditions compared with the sprinkler layout
- Recommendation
- Revise the design and confirm with the fire consultant
Which stage should you audit?
Before tender or contract award to fix gaps cheaply, during construction to control quality, progress and payments, and at completion to check handover documents and the final account. See the pre-construction, construction and post-construction audits.
Frequently asked questions
What is different about auditing an industrial project?
- Industrial projects are often fast-track and design-and-build, with heavy loads, large spans, process equipment and services that must fit together, and strict fire, environmental and factory approvals. The audit checklist is adapted to these risks.
Do you audit EPC and design-and-build contracts?
- Yes. We check the employer's requirements against the contractor's design, the payment milestones against progress, and the variation and claim records.
Do you audit process equipment?
- We check the building and services interfaces with process equipment, such as foundations, openings, loads and utilities. Specialist process performance is outside our scope unless agreed with a specialist partner.
Can you audit a plant that is already operating?
- Yes, a post-construction audit can review as-builts, records, defects and the final account for a completed or operating facility.