Post-construction audit: handover and final account

A post-construction audit checks a project at completion and handover. CloudBrain Project Audit reviews as-built drawings, snag and defect lists, testing and commissioning records, warranties and O&M manuals, and reconciles the final bill and final account against the contract, so owners take over a building that is complete, documented and correctly paid for.

This is an independent technical and commercial project audit. It is not a statutory financial audit, which in India is carried out by chartered accountants.

What does a post-construction audit check?

  • As-built drawings: whether they reflect what was built and are complete for every discipline.
  • Snags and defects: snag lists checked on site and against records, with open items and responsibilities.
  • Testing and commissioning: records for structural, services and safety systems, and anything not yet tested.
  • Warranties and O&M manuals: completeness, validity and whether a facility team can use them.
  • Final bill and final account: reconciled against the contract, approved variations, measurements and earlier running bills.
  • Retention and defects liability: what is held, when it falls due, and the defects to notify before the period ends.
Post-construction audit: key facts
WhenBefore handover and the final payment, and before the end of the defects liability period
What we checkAs-builts, snags and defects, testing and commissioning, warranties, O&M manuals, final bill and final account
OutputsA findings report, an open-items list for handover, and a reconciliation of the final account
Typical durationTypically 2–4 weeks; a final account review depends on the size of the contract
DeliveryDocument review remotely, with a site walkthrough in India directly and elsewhere by arrangement
  1. Design and tender
  2. Construction
  3. Handover
  4. Defects liability period
The highlighted stage is when this audit takes place.
A hand holding keys in front of a finished home's entrance
Handover is the last point where gaps in records and works are cheap to fix.

What documents do we ask for?

  • As-built drawings for every discipline
  • Snag and defect lists with close-out status
  • Testing and commissioning records and certificates
  • O&M manuals, warranties and the asset register
  • Final bill, final account statement and earlier running bills
  • Retention, bank guarantee and defects liability period details

What does the post-construction checklist cover?

Handover

  • As-built drawings reflect the built works for every discipline
  • Snag list is complete, with owners and close-out dates
  • Testing and commissioning is complete for every system

Documents

  • O&M manuals, warranties and the asset register are complete and usable
  • Statutory completion and occupancy approvals are in hand

Final account

  • Final quantities reconcile with measurements and earlier bills
  • Every variation in the final account is approved and priced per contract
  • Retention and guarantees are tracked to the end of the defects liability period

See all stages on the audit checklists page.

An electrician testing an electrical panel with a multimeter
Testing and commissioning records are checked for every building system.

What does a typical finding look like?

These are illustrative examples of the kind of findings a post-construction audit reports. They are not from a real project.

HandoverMediumIllustrative example, not a real project

No commissioning records for the fire pump set

Evidence
Commissioning file compared with the systems list
Recommendation
Commission and record before accepting handover
As-built drawingsMediumIllustrative example, not a real project

As-built plumbing drawings show the original riser locations, not the relocated risers on site

Evidence
Site inspection compared with drawing P-AB-04
Recommendation
Update the as-built drawings before the facility team takes over
Final accountHighIllustrative example, not a real project

A variation for additional external paving is included twice in the final account

Evidence
Final account statement compared with the variation register and earlier running bills
Recommendation
Remove the duplicate before the final payment
Defects liabilityLowIllustrative example, not a real project

Defects liability end date is not recorded against the retention held

Evidence
Retention register and the completion certificate
Recommendation
Record the date and diarise a defects inspection before it ends

When should you commission it?

Before accepting handover and making the final payment, and again a few months before the defects liability period ends.

What do you get?

A written report with an open-items list for handover, a reconciliation of the final account with the items to hold or correct, and a short summary for decision makers.

Frequently asked questions

What does a post-construction audit include?

A review of as-built drawings, snag and defect lists, testing and commissioning records, warranties and guarantees, O&M manuals and handover documents, and a reconciliation of the final bill and final account against the contract.

Can you check the final account?

Yes. We reconcile the final account against the contract, approved variations, measurements and earlier running bills, and list items that are unsupported, duplicated or incorrectly priced.

Why audit before the end of the defects liability period?

Defects that are recorded and notified within the period are usually the contractor's responsibility to fix. After it ends, the cost normally falls on the owner.

Do you help with facility management handover?

We check that the documents a facility team needs, such as as-builts, O&M manuals, warranties and asset lists, are complete and usable, and list what is missing.