What does a post-construction audit check?
- As-built drawings: whether they reflect what was built and are complete for every discipline.
- Snags and defects: snag lists checked on site and against records, with open items and responsibilities.
- Testing and commissioning: records for structural, services and safety systems, and anything not yet tested.
- Warranties and O&M manuals: completeness, validity and whether a facility team can use them.
- Final bill and final account: reconciled against the contract, approved variations, measurements and earlier running bills.
- Retention and defects liability: what is held, when it falls due, and the defects to notify before the period ends.
| When | Before handover and the final payment, and before the end of the defects liability period |
|---|---|
| What we check | As-builts, snags and defects, testing and commissioning, warranties, O&M manuals, final bill and final account |
| Outputs | A findings report, an open-items list for handover, and a reconciliation of the final account |
| Typical duration | Typically 2–4 weeks; a final account review depends on the size of the contract |
| Delivery | Document review remotely, with a site walkthrough in India directly and elsewhere by arrangement |
- Design and tender
- Construction
- Handover
- Defects liability period

What documents do we ask for?
- As-built drawings for every discipline
- Snag and defect lists with close-out status
- Testing and commissioning records and certificates
- O&M manuals, warranties and the asset register
- Final bill, final account statement and earlier running bills
- Retention, bank guarantee and defects liability period details
What does the post-construction checklist cover?
Handover
- As-built drawings reflect the built works for every discipline
- Snag list is complete, with owners and close-out dates
- Testing and commissioning is complete for every system
Documents
- O&M manuals, warranties and the asset register are complete and usable
- Statutory completion and occupancy approvals are in hand
Final account
- Final quantities reconcile with measurements and earlier bills
- Every variation in the final account is approved and priced per contract
- Retention and guarantees are tracked to the end of the defects liability period
See all stages on the audit checklists page.

What does a typical finding look like?
These are illustrative examples of the kind of findings a post-construction audit reports. They are not from a real project.
No commissioning records for the fire pump set
- Evidence
- Commissioning file compared with the systems list
- Recommendation
- Commission and record before accepting handover
As-built plumbing drawings show the original riser locations, not the relocated risers on site
- Evidence
- Site inspection compared with drawing P-AB-04
- Recommendation
- Update the as-built drawings before the facility team takes over
A variation for additional external paving is included twice in the final account
- Evidence
- Final account statement compared with the variation register and earlier running bills
- Recommendation
- Remove the duplicate before the final payment
Defects liability end date is not recorded against the retention held
- Evidence
- Retention register and the completion certificate
- Recommendation
- Record the date and diarise a defects inspection before it ends
When should you commission it?
Before accepting handover and making the final payment, and again a few months before the defects liability period ends.
What do you get?
A written report with an open-items list for handover, a reconciliation of the final account with the items to hold or correct, and a short summary for decision makers.
Frequently asked questions
What does a post-construction audit include?
- A review of as-built drawings, snag and defect lists, testing and commissioning records, warranties and guarantees, O&M manuals and handover documents, and a reconciliation of the final bill and final account against the contract.
Can you check the final account?
- Yes. We reconcile the final account against the contract, approved variations, measurements and earlier running bills, and list items that are unsupported, duplicated or incorrectly priced.
Why audit before the end of the defects liability period?
- Defects that are recorded and notified within the period are usually the contractor's responsibility to fix. After it ends, the cost normally falls on the owner.
Do you help with facility management handover?
- We check that the documents a facility team needs, such as as-builts, O&M manuals, warranties and asset lists, are complete and usable, and list what is missing.