Construction project audit checklists

These checklists show what a CloudBrain project audit checks at each stage of a construction project: design, cost and contracts before work starts; quality, billing, progress and records during construction; and handover documents and the final account at the end. Each stage also lists the documents we ask for.

Download the full checklist

The complete checklist as a free 16-page A4 PDF: every check for each stage with Yes, No and N/A boxes, a severity scale, document request lists and a blank findings register.
Cover of the Construction Project Audit Checklist

Construction Project Audit Checklist

PDF · 16 pages · A4

First edition · November 2026

Pre-construction audit

What do we check before construction starts?

  1. Design and tender
  2. Construction
  3. Handover
  4. Defects liability period
The highlighted stage is when this audit takes place.

Design

  • Drawings meet the brief: areas, functions and specifications
  • Design complies with the codes and approvals that apply (for example NBC 2016, or local codes)
  • Architectural, structural and MEP drawings are coordinated, with no clashes at key junctions
  • Details are buildable with the materials and methods specified

Cost and BOQ

  • BOQ quantities for major items match the drawings
  • No missing, duplicated or vague items; provisional sums are justified
  • Item descriptions match the specifications

Contracts and approvals

  • Scope, interfaces and responsibilities are clear between packages
  • Payment, variation, escalation and retention terms are workable
  • Required approvals are in hand, or planned in the programme

Documents we ask for

  • Client brief and design basis report
  • Architectural, structural and MEP drawings with their revision register
  • Specifications and the BOQ with the cost estimate
  • Tender documents, draft contract and conditions of contract
  • Approvals obtained and pending, with their conditions
  • Programme and the project risk register

More about the pre-construction audit →

Construction stage audit

What do we check during construction?

  1. Design and tender
  2. Construction
  3. Handover
  4. Defects liability period
The highlighted stage is when this audit takes place.

Quality

  • Inspection and test plan exists and is followed for each activity
  • Material test certificates match the materials and batches used
  • Workmanship inspected on site matches the drawings and specifications
  • Non-conformances are recorded, corrected and closed

Billing

  • Billed quantities match measurements and approved drawings
  • Rates match the contract; non-tender items are approved
  • Advances, recoveries, deductions and retention are applied correctly

Progress, records and safety

  • Progress matches the programme; delays have causes and a recovery plan
  • Drawings on site are the current revision
  • Safety plan, permits to work and incident records are in place

Documents we ask for

  • Contract, approved drawings and current revision register
  • QA/QC plan, inspection and test plans, material test certificates
  • Running account bills with the measurement book or measurement sheets
  • Variation and change-order register with approvals
  • Programme, progress reports and minutes of meetings
  • Site diary, RFI register, non-conformance reports and safety records

More about the construction stage audit →

Post-construction audit

What do we check at completion and handover?

  1. Design and tender
  2. Construction
  3. Handover
  4. Defects liability period
The highlighted stage is when this audit takes place.

Handover

  • As-built drawings reflect the built works for every discipline
  • Snag list is complete, with owners and close-out dates
  • Testing and commissioning is complete for every system

Documents

  • O&M manuals, warranties and the asset register are complete and usable
  • Statutory completion and occupancy approvals are in hand

Final account

  • Final quantities reconcile with measurements and earlier bills
  • Every variation in the final account is approved and priced per contract
  • Retention and guarantees are tracked to the end of the defects liability period

Documents we ask for

  • As-built drawings for every discipline
  • Snag and defect lists with close-out status
  • Testing and commissioning records and certificates
  • O&M manuals, warranties and the asset register
  • Final bill, final account statement and earlier running bills
  • Retention, bank guarantee and defects liability period details

More about the post-construction audit →

How are the checks applied?

Checklists set the minimum. The audit team adapts them to the project type and the concerns in the scope, samples large registers and bills, and rates every finding for severity. See how we audit and a sample report.

This is an independent technical and commercial project audit. It is not a statutory financial audit, which in India is carried out by chartered accountants.

Request a project audit

Find out where your project stands

Tell us about the project, its stage and what worries you most. We'll propose an audit scope, the documents we need and whether site visits are required.