| F-01 | Design | High | Stair width on the second escape stair is below the minimum for the occupant loadEvidence: Architectural drawing A-201, revision C, compared with the fire and life safety requirements that applyImpact: Risk to fire approval and occupant safety; redesign cost rises after construction starts | Revise the stair design and confirm with the fire consultant before tender | Open |
|---|
| F-02 | Design | Medium | Main HVAC duct clashes with a beam at level 3, grid C–DEvidence: Overlay of structural drawing S-310 and HVAC drawing M-305Impact: Site rework and loss of ceiling height if not resolved | Coordinate a revised duct route; issue a coordinated drawing | Open |
|---|
| F-03 | Quality | High | Cube test results missing for two slab poursEvidence: Pour register compared with the concrete test register for the sampled monthImpact: Concrete strength for those slabs cannot be demonstrated | Locate the records or commission in-situ testing; hold related payments | Open |
|---|
| F-04 | Billing | High | Running bill claims the full slab area; the drawing shows a 12 m² opening not deductedEvidence: Measurement sheet for the sampled bill compared with structural drawing S-402Impact: Overpayment if the item is not corrected | Re-measure and correct the quantity in the next bill | Open |
|---|
| F-05 | Billing | Medium | Non-tender item paid at a rate that was not approvedEvidence: Bill extract and the variation register; no rate approval on fileImpact: Payment without contractual basis | Obtain rate analysis and approval, or recover the difference | Open |
|---|
| F-06 | Documentation | Medium | Superseded drawing revisions in use on site for one blockEvidence: Site inspection compared with the drawing register (photo log, item 14)Impact: Risk of work built to an outdated design | Withdraw superseded drawings; set up a controlled drawing issue process | Open |
|---|
| F-07 | Approvals | High | A condition of the environmental clearance has no compliance recordEvidence: Approval conditions compared with the compliance fileImpact: Regulatory risk at completion and occupancy | Assign an owner and record compliance before the next stage | Open |
|---|
| F-08 | Health, safety and environment | Critical | Edge protection missing at an open slab edge on an upper floorEvidence: Site inspection, photo log item 22Impact: Immediate risk of a fall from height | Stop work in the area until edge protection is installed and checked | Closed on the day |
|---|
| F-09 | Handover | Medium | No commissioning records for the fire pump setEvidence: Commissioning file compared with the systems listImpact: Fire system performance cannot be demonstrated at handover | Commission and record before accepting handover | Open |
|---|
| F-10 | Contracts and claims | Observation | Delay notices are filed, but not linked to the programme updatesEvidence: Correspondence file and programme revisionsImpact: Weakens the record if an extension of time is disputed later | Link each notice to the programme activity it affects | Noted |
|---|