CloudBrain Project Audit
How a CloudBrain project audit works
This is an independent technical and commercial project audit. It is not a statutory financial audit, which in India is carried out by chartered accountants.
What principles guide every audit?
Independent
The audit team reports to whoever commissions the audit and has no role in designing, building or certifying the project being audited.
Evidence for every finding
Each finding cites its evidence: a drawing or clause reference, a measurement, a test record or a dated photograph.
Risk-based sampling
Large registers and bills are sampled, with more weight on high-value, high-risk and unusual items, and the sample is stated in the report.
Confidential
Project documents are used only for the audit, held under the client's confidentiality terms and India's DPDP Act, 2023, and returned or deleted at the end.
What are the steps of an audit?
- Enquiry and conflict check
- Scope and engagement letter
- Document request list
- Desk review
- Site inspection
- Findings and severity rating
- Draft report and factual check
- Final report and walkthrough
- Follow-up and close-out
Step 01
Enquiry and conflict check
- Inputs
- Project brief, stage, location and who is commissioning the audit
- What we do
- Confirm we have no role on the project and no conflict of interest; understand the main concern
- Output
- Go or no-go, and a first view of the audit areas
- Who
- Audit lead
Step 02
Scope and engagement letter
- Inputs
- Concerns, stage, project size and the areas to cover
- What we do
- Agree the audit areas, sample sizes, site visits, reporting format and confidentiality terms
- Output
- Signed engagement letter with scope, limitations and deliverables
- Who
- Audit lead and client
Step 03
Document request list
- Inputs
- Agreed scope
- What we do
- Issue a request list for the stage (drawings, contracts, BOQ, bills, registers, test records) and set up a shared folder
- Output
- Indexed document set, with gaps listed
- Who
- Audit coordinator
Step 04
Desk review
- Inputs
- Indexed documents
- What we do
- Review design, contracts, bills, schedules and records against the brief, the contract and the codes that apply; select samples
- Output
- Draft findings and a list of points to verify on site
- Who
- Architect, engineers, QS, QA/QC and, for commercial areas, the chartered accountant
Step 05
Site inspection
- Inputs
- Points to verify, sample locations, safety induction
- What we do
- Inspect works and records on site, measure samples, photograph evidence, interview the site team
- Output
- Site notes, measurements and a dated photo log
- Who
- Civil and MEP engineers, QA/QC specialist
Step 06
Findings and severity rating
- Inputs
- Desk and site evidence
- What we do
- Write each finding with its evidence, impact and recommended action; rate its severity on the five-level scale
- Output
- Findings register
- Who
- Audit team, reviewed by the audit lead
Step 07
Draft report and factual check
- Inputs
- Findings register
- What we do
- Share the draft so the project team can correct factual errors; record their responses
- Output
- Draft report with management responses
- Who
- Audit lead and project team
Step 08
Final report and walkthrough
- Inputs
- Draft report and responses
- What we do
- Issue the final report with an executive summary, and walk decision makers through the findings
- Output
- Final report, findings register and photo log
- Who
- Audit lead
Step 09
Follow-up and close-out
- Inputs
- Agreed actions and owners
- What we do
- Re-check that actions were closed, or plan the audit for the next stage
- Output
- Close-out note, or the next audit's scope
- Who
- Audit team (optional)
How are findings rated?
| Severity | What it means | Expected action |
|---|---|---|
| Critical | A risk to safety, structural integrity or legal compliance, or a major financial exposure. | Act immediately; stop or hold the related work or payment. |
| High | A significant cost, time or quality risk if it is not corrected. | Correct before the next milestone or payment. |
| Medium | A departure from the contract, specification or good practice with a moderate impact. | Correct within an agreed period. |
| Low | A minor gap in records or process with little direct impact. | Correct during normal work. |
| Observation | Not a defect: a suggestion to improve control, records or efficiency. | Consider; no action required. |
What counts as evidence?
- Drawing, specification or contract references (number, revision and clause)
- Measurements with the method, location and date
- Test certificates and inspection records, matched to the work they cover
- Dated, located photographs in a photo log
- Notes of interviews with the site and project teams
How do you sample?
Registers, bills and inspection locations are sampled rather than checked in full, with more weight on high-value, high-risk and unusual items. The sample and the method are stated in the report, and widened where a pattern of errors appears.
How is our data handled?
Project documents are used only for the audit, kept under the client's confidentiality terms and India's Digital Personal Data Protection Act, 2023, and returned or deleted when the audit closes.

Who does what in an audit team?
| Role | Responsible for |
|---|---|
| Audit lead | Scope, quality of findings, the report and the walkthrough |
| Architect | Design against the brief, codes and approvals; coordination; handover drawings |
| Civil and structural engineer | Structure, civil works, quality records, measurements |
| MEP engineer | Building services design, installation, testing and commissioning |
| Quantity surveyor | BOQ, measurements, bills, variations and the final account |
| QA/QC specialist | Quality plans, inspection and test plans, non-conformances |
| Chartered accountant | Commercial and contractual records behind payments (not a statutory audit) |
The team for each audit depends on the project type and the areas in scope.
How long does an audit take?
Typically 2–4 weeks for a pre-construction or post-construction audit, and 3–6 weeks for a single construction-stage audit, or monthly or milestone visits for the life of the project. We agree the exact timeline in the engagement letter. It depends on:
- The stage and the number of audit areas in scope
- Project size, and how many contracts and packages there are
- How complete and organised the documents are
- Whether site visits are needed, and where the site is
- Sample sizes agreed for bills, registers and inspections
Frequently asked questions
Do you share findings with the contractor or consultant being audited?
- Only as agreed with whoever commissions the audit. Usually the draft report goes to the project team for a factual-accuracy check, and their responses are recorded in the final report.
What happens if you find a safety risk?
- Critical findings, such as a risk of a fall from height, are reported on the same day to the person named in the engagement letter, not held back for the report.
Do you check every bill item and every drawing?
- Not usually. Large registers and bills are sampled, with more weight on high-value, high-risk and unusual items. The sample and the method are stated in the report, and the sample can be widened where a pattern of errors appears.