How a CloudBrain project audit works

Every CloudBrain project audit follows the same nine-step procedure, from a conflict check and an agreed scope to a desk review, site inspection, rated findings, a factual check with the project team, a final report and follow-up. Every finding cites its evidence and carries one of five severity ratings, from Critical to Observation.

This is an independent technical and commercial project audit. It is not a statutory financial audit, which in India is carried out by chartered accountants.

What principles guide every audit?

  • Independent

    The audit team reports to whoever commissions the audit and has no role in designing, building or certifying the project being audited.

  • Evidence for every finding

    Each finding cites its evidence: a drawing or clause reference, a measurement, a test record or a dated photograph.

  • Risk-based sampling

    Large registers and bills are sampled, with more weight on high-value, high-risk and unusual items, and the sample is stated in the report.

  • Confidential

    Project documents are used only for the audit, held under the client's confidentiality terms and India's DPDP Act, 2023, and returned or deleted at the end.

What are the steps of an audit?

The same nine steps apply at every stage; the documents and checks change with the stage and the areas in scope.
  1. Enquiry and conflict check
  2. Scope and engagement letter
  3. Document request list
  4. Desk review
  5. Site inspection
  6. Findings and severity rating
  7. Draft report and factual check
  8. Final report and walkthrough
  9. Follow-up and close-out
  1. Step 01

    Enquiry and conflict check

    Inputs
    Project brief, stage, location and who is commissioning the audit
    What we do
    Confirm we have no role on the project and no conflict of interest; understand the main concern
    Output
    Go or no-go, and a first view of the audit areas
    Who
    Audit lead
  2. Step 02

    Scope and engagement letter

    Inputs
    Concerns, stage, project size and the areas to cover
    What we do
    Agree the audit areas, sample sizes, site visits, reporting format and confidentiality terms
    Output
    Signed engagement letter with scope, limitations and deliverables
    Who
    Audit lead and client
  3. Step 03

    Document request list

    Inputs
    Agreed scope
    What we do
    Issue a request list for the stage (drawings, contracts, BOQ, bills, registers, test records) and set up a shared folder
    Output
    Indexed document set, with gaps listed
    Who
    Audit coordinator
  4. Step 04

    Desk review

    Inputs
    Indexed documents
    What we do
    Review design, contracts, bills, schedules and records against the brief, the contract and the codes that apply; select samples
    Output
    Draft findings and a list of points to verify on site
    Who
    Architect, engineers, QS, QA/QC and, for commercial areas, the chartered accountant
  5. Step 05

    Site inspection

    Inputs
    Points to verify, sample locations, safety induction
    What we do
    Inspect works and records on site, measure samples, photograph evidence, interview the site team
    Output
    Site notes, measurements and a dated photo log
    Who
    Civil and MEP engineers, QA/QC specialist
  6. Step 06

    Findings and severity rating

    Inputs
    Desk and site evidence
    What we do
    Write each finding with its evidence, impact and recommended action; rate its severity on the five-level scale
    Output
    Findings register
    Who
    Audit team, reviewed by the audit lead
  7. Step 07

    Draft report and factual check

    Inputs
    Findings register
    What we do
    Share the draft so the project team can correct factual errors; record their responses
    Output
    Draft report with management responses
    Who
    Audit lead and project team
  8. Step 08

    Final report and walkthrough

    Inputs
    Draft report and responses
    What we do
    Issue the final report with an executive summary, and walk decision makers through the findings
    Output
    Final report, findings register and photo log
    Who
    Audit lead
  9. Step 09

    Follow-up and close-out

    Inputs
    Agreed actions and owners
    What we do
    Re-check that actions were closed, or plan the audit for the next stage
    Output
    Close-out note, or the next audit's scope
    Who
    Audit team (optional)

How are findings rated?

Each finding gets one of five ratings, so decision makers can see at a glance what needs action first.
Finding severity scale
SeverityWhat it meansExpected action
CriticalA risk to safety, structural integrity or legal compliance, or a major financial exposure.Act immediately; stop or hold the related work or payment.
HighA significant cost, time or quality risk if it is not corrected.Correct before the next milestone or payment.
MediumA departure from the contract, specification or good practice with a moderate impact.Correct within an agreed period.
LowA minor gap in records or process with little direct impact.Correct during normal work.
ObservationNot a defect: a suggestion to improve control, records or efficiency.Consider; no action required.

What counts as evidence?

  • Drawing, specification or contract references (number, revision and clause)
  • Measurements with the method, location and date
  • Test certificates and inspection records, matched to the work they cover
  • Dated, located photographs in a photo log
  • Notes of interviews with the site and project teams

How do you sample?

Registers, bills and inspection locations are sampled rather than checked in full, with more weight on high-value, high-risk and unusual items. The sample and the method are stated in the report, and widened where a pattern of errors appears.

How is our data handled?

Project documents are used only for the audit, kept under the client's confidentiality terms and India's Digital Personal Data Protection Act, 2023, and returned or deleted when the audit closes.

Rows of labelled ring binders on office shelves
Registers, certificates and correspondence are indexed before the desk review.

Who does what in an audit team?

Audit team roles
RoleResponsible for
Audit leadScope, quality of findings, the report and the walkthrough
ArchitectDesign against the brief, codes and approvals; coordination; handover drawings
Civil and structural engineerStructure, civil works, quality records, measurements
MEP engineerBuilding services design, installation, testing and commissioning
Quantity surveyorBOQ, measurements, bills, variations and the final account
QA/QC specialistQuality plans, inspection and test plans, non-conformances
Chartered accountantCommercial and contractual records behind payments (not a statutory audit)

The team for each audit depends on the project type and the areas in scope.

How long does an audit take?

Typically 2–4 weeks for a pre-construction or post-construction audit, and 3–6 weeks for a single construction-stage audit, or monthly or milestone visits for the life of the project. We agree the exact timeline in the engagement letter. It depends on:

  • The stage and the number of audit areas in scope
  • Project size, and how many contracts and packages there are
  • How complete and organised the documents are
  • Whether site visits are needed, and where the site is
  • Sample sizes agreed for bills, registers and inspections

Frequently asked questions

Do you share findings with the contractor or consultant being audited?

Only as agreed with whoever commissions the audit. Usually the draft report goes to the project team for a factual-accuracy check, and their responses are recorded in the final report.

What happens if you find a safety risk?

Critical findings, such as a risk of a fall from height, are reported on the same day to the person named in the engagement letter, not held back for the report.

Do you check every bill item and every drawing?

Not usually. Large registers and bills are sampled, with more weight on high-value, high-risk and unusual items. The sample and the method are stated in the report, and the sample can be widened where a pattern of errors appears.

Find out where your project stands

Tell us about the project, its stage and what worries you most. We'll propose an audit scope, the documents we need and whether site visits are required.