Why audit the design before tender?
A design problem found on paper costs a drawing revision. The same problem found on site can cost demolition, delay and a variation claim at a non-competitive rate. A pre-construction audit is the cheapest point to find gaps.
What should you check?
- Brief and codes: areas, functions and specifications match the brief; the design meets the codes that apply, such as the National Building Code of India, and local bye-laws.
- Fire and life safety: escape routes, stairs, compartments and fire services.
- Coordination: architectural, structural and services drawings share grids and levels, with no clashes at key junctions.
- Constructability: details can be built with the specified materials and methods.
- BOQ: quantities for major items match the drawings, with no missing or duplicated items.
- Contracts: scope, interfaces, payment, variation and escalation terms are clear.
- Approvals and programme: approvals are in hand or planned, and the programme is realistic.
The full list is in our audit checklists.
What does a typical finding look like?
Illustrative example, not a real project: waterproofing to the basement walls is shown on the drawings but missing from the BOQ. Left as it is, it becomes a certain variation after award. The recommendation is to add the item, with quantities, before tender.
What documents do you need?
- The client brief and the design basis report
- Architectural, structural and MEP drawings with their revision register
- Specifications, the BOQ and the cost estimate
- Tender documents: conditions of contract, scope and interfaces between packages
- Approvals obtained or applied for, and their conditions
- The programme and the risk register
How does a pre-construction design audit work?
- Agree the scope. Which areas are in scope (design, cost, contracts, approvals), which drawings and which revision, and what is out of scope.
- Review against the brief and the codes. Areas, functions and specifications against the brief, and the design against the codes and bye-laws that apply where the project is.
- Check coordination. Overlay architectural, structural and services drawings at grids, levels, shafts and congested junctions.
- Test the BOQ. Take off the main items from the drawings and compare them with the BOQ, looking for missing, duplicated or vague items.
- Read the contract documents. Scope gaps between packages, payment, variation and escalation terms, and how risk is allocated.
- Report. Each finding with its evidence, a severity rating and a recommended action, plus a summary for decision makers.
Which gaps are most common?
- Items on the drawings that are missing from the BOQ, or described differently in the specification
- Services routes that clash with beams or reduce clear heights
- Scope that falls between two packages, such as builder's work for MEP or external works
- Approvals assumed in the programme but not yet applied for
- Provisional sums and allowances with no basis
How long does it take?
Typically 2–4 weeks, depending on the size of the project, the number of packages and how complete the drawings are.
How can CloudBrain help?
A pre-construction audit by CloudBrain Project Audit reviews the design, BOQ, contract documents and approvals before tender, and reports each finding with its evidence and a recommended fix.
Frequently asked questions
When is the best time for a pre-construction audit?
- After design development and before tender. A second, shorter check before contract award catches changes made to the tender package.
Does a design audit replace the design team's own checks?
- No. The design team stays responsible for the design. An independent audit is an extra check, focused on gaps, risks and cost exposure.
What are typical findings?
- Code compliance gaps such as escape stair widths, clashes between beams and ducts, items shown on drawings but missing from the BOQ, and interfaces between packages that no contract covers.