Why does inspection and test plan matter in a construction project audit?
Without ITPs, quality depends on chance. Audits check that each major activity has an ITP and that inspections were actually recorded before work was covered up.
What is an example?
An ITP for slab concreting lists checks on formwork, reinforcement and cover before the pour, slump and cube tests during it, and curing records after it, each with a hold point and sign-off.